Ministry/Agency: Ministry of
Shipping/BIWTA
Project start date: 31 December 2023
Project duration: 30 June 2026
Project progress percentage: 68%
Time elapsed: 66%
Joint business partner: S.S. Rahman
International Ltd
Current status of the project: Work is
progressing slowly due to lack of new alignment.