Ministry/Organization: Ministry of
Shipping/Payra Port Authority
Project Start Date: 19 November 2018
Project Duration: 30 June 2025
(Duration Extension Process Underway)
Work Details: Number of Buildings- 193
(A Type 37 and B Type 156)
Project Progress Percentage: 90%
Time Elapsed: 100%
Joint Business Partner: Kanak
Construction Co.
Project Challenges:
Due to the limited capacity of the JV organization, efforts are ongoing to
complete the work by providing financial support from this organization.