Dredging work by Cutter suction Dredger for Maintaining Navigavility

Ministry/Agency: Ministry of Shipping/BIWTA

Project start date: 31 December 2023

Project duration: 30 June 2026

Project progress percentage: 48%

Time elapsed: 66%

Joint business partner: SS Dredgers and Engineers Co. Ltd

Project challenge: Work cannot be started due to lack of demand for Rooppur Nuclear Power Plant.

Current status of the project: Work is stopped.