Ministry/Agency: Ministry of
Shipping/BIWTA
Project start date: 31 December 2023
Project duration: 30 June 2026
Project progress percentage: 57%
Time elapsed: 66%
Joint business partner: First SS
Current status of the project:
Pre-survey for new alignment is in process.