Payra Rehabilitation Project, Dhulasar, Kalapara, Patuakhali (Package-

Ministry/Organization: Ministry of Shipping/Payra Port Authority

Project Start Date: 19 November 2018

Project Duration: 30 June 2025 (Duration Extension Process Underway)

          Work Details: Number of Buildings: 270 (B Type 270) (2 Type A and 132 Type B buildings have been handed over in Packages 9 and 10)

Project Progress Percentage: 98%

Time Elapsed: 100%

Joint Business Partner: M. M. Builders and Engineers Ltd

Project Challenges: Due to complications in land acquisition and selection of allottees, it is not possible to hand over the buildings on time.